9am
- Continue doing the presentation slides
- Have a preview on the previous presentation slides
- Discuss some information and detail should be added into the slides
- Have a preview on the milestone and design plan of golf villa site and P4,P5,P26 lamp site
2pm
- Visit cross sea bridge street lamp construction site
- The construction work is delayed and the landscape project is completed, however the landscape should be done right after the lamp installation
- Taking photos that could added into the slides
- Visit golf resort site
- Taking photos that could added into the slides
- Check the pump is in good condition (water pressure is around 5 bar--->normal)
- Visit site where the location amendment of water and power supply pipe project implement
- Contact the person who responsible for marking locations
- Observe the expert using specific machine to do marking
- Taking photos that could added into the slides
- Contact the contractor that he could start the construction work
5pm
- Back to the office
- Add photos along with explanation on the progress into the presentation slides
- Complete and submit the slides to supervisor
- Correct some mistakes after being viewed by supervisor
6pm
- Off from work