Day 46 Internship at Forest City
by BOO WEN HAO
Day 46 Internship at Forest City
9am
- Visit P26 site region
- The crossroad DN900 sewage pipe construction is completed
- Inform the contractor to fast sand backfilling
- Inform the contractor to transport the concrete pieces that served as the temporary road base
- Inform all the related department that the road will be recovered soon during this afternoon
- There's still left 4 crossroad pipe for Elv, using equipment break road structure first then will choose one day to proceed
- Start the 20meter sewage pipe construction at front end (dig trenches, check elevation level using instrument, manhole, installing pipes)
- Problem: Awaiting cement mixture for foundation
2pm
- Visit P26 site region
- The road is perfectly recovered and ready to open to traffic
- Check the sewage pipe construction along P26
- At front end, found some part haven't sand backfilling, take photos and inform the contractor to complete it
- At rear end, there is part without putting the cement mixture on the top of sewage pipe, awaiting cement mixture
- Along middle part, the trenches are done but the DN600 sewage pipe estimated will reach by tonight
- All the DN600 pipe can be installed by tomorrow and sandbackfilling hence estimated left 50m undone
- Inform the contractor to do the sewage pipe connections to Sewage Treatment Plant (STP)
2. Visit P52 site region
- Verify the location for airflow orifice pipe together with the contractor who handling the STP construction
- Inform the contractor can start the airflow orifice pipe by tomorrow as the road foundation construction already start
6pm
- Off from work