Industrial training logbook

Day 46 Internship at Forest City

Day 46 Internship at Forest City

9am

  1. Visit P26 site region
  • The crossroad DN900 sewage pipe construction is completed
  • Inform the contractor to fast sand backfilling
  • Inform the contractor to transport the concrete pieces that served as the temporary road base
  • Inform all the related department that the road will be recovered soon during this afternoon
  • There's still left 4 crossroad pipe for Elv, using equipment break road structure first then will choose one day to proceed 
  • Start the 20meter sewage pipe construction at front end (dig trenches, check elevation level using instrument, manhole, installing pipes)
  • Problem: Awaiting cement mixture for foundation

2pm

  1. Visit P26 site region
  • The road is perfectly recovered and ready to open to traffic
  • Check the sewage pipe construction along P26
  • At front end, found some part haven't sand backfilling, take photos and inform the contractor to complete it
  • At rear end, there is part without putting the cement mixture on the top of sewage pipe, awaiting cement mixture
  • Along middle part, the trenches are done but the DN600 sewage pipe estimated will reach by tonight
  • All the DN600 pipe can be installed by tomorrow and sandbackfilling hence estimated left 50m undone
  • Inform the contractor to do the sewage pipe connections to Sewage Treatment Plant (STP)

         2. Visit P52 site region

  • Verify the location for airflow orifice pipe together with the contractor who handling the STP construction
  • Inform the contractor can start the airflow orifice pipe by tomorrow as the road foundation construction already start

6pm

  • Off from work