Day 35 Internship at Forest City
by BOO WEN HAO
Day 35 Internship at Forest City
9am
- Visit International School region
- 2 well are closed and completed but only left 3 wells
2. Visit P4 site region
- Most high voltage power supply well are installed and awaiting sand backfilling process
- Inform the contractor to do housekeeping and make sure the site is clean and ease for others's construction
- Take photos that could be added in the work memo
3. Visit P26 site region
- Contractor now facing short manpower and delay due to bad weather
4. Visit region under bridge where exist DN1000 water supply piping
- Meet with the SAJ Ranhill person in charge for inspection
- Observe the inspection process
- SAJ found out some problems that are not following the specifications, jot down and write comment
2pm
- Visit site where exist temporary sewage treatment plant
- Meet with the technician and found out the problem
- Discuss the available solutions
2. Visit P4 site region
- Gather up the road and bridge contractor, piping contractor and road and bridge department PIC at site
- Together visit the site and mention own problems
- Coordinate and discuss the solutions
3. Visit P26 site region
- Check the progress
- Contractor facing short manpower
- The sewage piping construction is seriously delayed
- Take photos that could added in the work memo
6pm
- Visit P4 site region
- Due to unaware to small municipal water supply pipe, result damage and leakage on pipe when digging trenches
- Quickly inform the contractor to bring the socket come on-site to fix it asap
- In the same time, install the last high voltage power supply well
- Inform the contractor to press on the on-site housekeeping issue as the materials leftover on site
7pm
- Off from work