Industrial training logbook

Day 35 Internship at Forest City

Day 35 Internship at Forest City

9am

  1. Visit International School region
  • 2 well are closed and completed but only left 3 wells

         2. Visit P4 site region

  • Most high voltage power supply well are installed and awaiting sand backfilling process
  • Inform the contractor to do housekeeping and make sure the site is clean and ease for others's construction
  • Take photos that could be added in the work memo

         3. Visit P26 site region

  • Contractor now facing short manpower and delay due to bad weather

         4. Visit region under bridge where exist DN1000 water supply piping

  • Meet with the SAJ Ranhill person in charge for inspection
  • Observe the inspection process
  • SAJ found out some problems that are not following the specifications, jot down and write comment

2pm

  1. Visit site where exist temporary sewage treatment plant
  • Meet with the technician and found out the problem
  • Discuss the available solutions

         2. Visit P4 site region

  • Gather up the road and bridge contractor, piping contractor and road and bridge department PIC at site
  • Together visit the site and mention own problems
  • Coordinate and discuss the solutions

         3. Visit P26 site region

  • Check the progress
  • Contractor facing short manpower
  • The sewage piping construction is seriously delayed
  • Take photos that could added in the work memo

6pm

  1. Visit P4 site region
  • Due to unaware to small municipal water supply pipe, result damage and leakage on pipe when digging trenches
  • Quickly inform the contractor to bring the socket come on-site to fix it asap
  • In the same time, install the last high voltage power supply well
  • Inform the contractor to press on the on-site housekeeping issue as the materials leftover on site

7pm

  • Off from work