Day 29 Internship at Forest CIty
by BOO WEN HAO
Day 29 Internship at Forest City
9am
- Visit P4 site region
- The high voltage power supply piping are installed about 60% and estimated to be complete by tomorrow
- Hence, will inform TNB come and install the cables
- Take some photos that could added in the presentation
- Check all the low voltage power supply well are closed properly
- Take some photos of uncovered well that could used as proof for penalty
2. Visit P26 site region
- At the front end of P26, the sewage piping construction still on progress
- Lot of sand leftover on-site and cause the other contractor unable to proceed the drainage construction
- Inform the contractor to arrange more lorries to come and remove all the sand
- At the middle part of P26, there still some building materials leftover that prohibit the construction from moving on
- Take some photos and add in the work memo hence send to the related department to request remove the materials, otherwise the construction will be delayed
- At the rear end of P26, also left much building materials although already inform them to move the things and the deadline is reached
- Take photos and add in the work memo to inform rapid allocation of materials so that the construction can be proceeded
- The amendment of drainage pipe is on progress and estimated to be completed by today
- Then, the sewage piping construction can be start by tomorrow
2pm
- Visit P26 site region
- At the middle part, already coordinate with the related department to move those materials in this afternoon
- The DN700 water supply pipe can be proceeded once the materials are moved
- Observe how the connections of pipe are done by using welding (only diameter greater than 700mm need inner and outer welding, less than 700mm only need outer welding)
- At the rear end part, the drainage pipe is moved 80% expected to be completed by today and tomorrow the sewage pipe construction can be started
- Inform the contractor to arrange the lorries to come and ship the sand out as it blocks the path for drainage pipe construction
2. Visit P4 site region
- Check the progress of the high-voltage power supply piping
- There is still left some part that could do the concrete foundation and urge the contractor come and do it
3. Visit International School region
- The well lid is lifted and awaiting the equipment to come and break the protruding well
5pm
- Back to office
- Do a table to write the progress of the integrated pipeline network (water, drainage, power supply, telekom, sewage) in different region
6pm
- Off from work