Day 32 Internship at Forest City
by BOO WEN HAO
Day 32 Internship at Forest City
9am
- Visit International School region
- The contractor change the machine for fixing the protruding well in order to make faster
2. Visit P26 site region
- At the front end, the low voltage power supply piping construction already ongoing and the well materials can already reach site and ready install
- At the middle part, the water supply piping construction already complete about 90%, left 130m
- Inform the contractor to install the water pressure meter and carry out the self-inspection to make sure the pressure can pumped up to 20bar
- Arrange the excessive sand to fill up the high voltage power supply piping
- Inform the contractor to find the air pressure holes
- At the rear end, inform the person in charge to clear all the things latest by today
- At the rear end, the low voltage power supply piping construction is initiated, then followed by the sewage piping construction
2pm
- Doing volunteer work for Country Garden
- Lead the primary school students for viewing the Forest City
- Explain to them about the background and development of Forest City
6pm
- Visit International School region
- Take photos and update to supervisor about the progress
2. Visit P4 site region
- Take photos and update to supervisor about the progress of high voltage power supply well
3. Visit P26 site region
- The water supply piping left 78meter and estimated completed by Saturday
- The air pressure test will be held by contractor for self inspection before SAJ comes
- Take photos and update to supervisor about the progress
7pm