9am

  1. Visit International School region
  • The contractor change the machine for fixing the protruding well in order to make faster

         2. Visit P26 site region

  • At the front end, the low voltage power supply piping construction already ongoing and the well materials can already reach site and ready install
  • At the middle part, the water supply piping construction already complete about 90%, left 130m
  • Inform the contractor to install the water pressure meter and carry out the self-inspection to make sure the pressure can pumped up to 20bar
  • Arrange the excessive sand to fill up the high voltage power supply piping
  • Inform the contractor to find the air pressure holes
  • At the rear end, inform the person in charge to clear all the things latest by today
  • At the rear end, the low voltage power supply piping construction is initiated, then followed by the sewage piping construction

IMG20180723103128.jpg

2pm

  1. Doing volunteer work for Country Garden
  • Lead the primary school students for viewing the Forest City
  • Explain to them about the background and development of Forest City

IMG20180720171944.jpg

6pm

  1. Visit International School region
  • Take photos and update to supervisor about the progress

         2. Visit P4 site region

  • Take photos and update to supervisor about the progress of high voltage power supply well

         3. Visit P26 site region

  • The water supply piping left 78meter and estimated completed by Saturday
  • The air pressure test will be held by contractor for self inspection before SAJ comes
  • Take photos and update to supervisor about the progress

7pm

  • Off from work