Industrial training logbook

Day 44 Internship at Forest City

Day 44 Internship at Forest City

9am

  1. Visit P26 site region
  • At the front end, the sewage pipe construction start and the foundation already complete
  • Being informed that the air pressure test at P26 site region will be launched by SAJ tomorrow morning
  • Inform the contractor to do the pre-test of air pressure for water supply pipe and make sure it can be pumped up to 17 bar
  • The DN600 corrugated HDPE pipe (sewage) will be reached by today afternoon
  • Inform the contractor to dig the trenches and do the concrete foundation prior installing the sewage pipe
  • Inform the contractor to sand backfilling the Elv pipe
  • Coordinate the related department to remove the concrete pieces so that the sewage pipe path are free from blockages

        2. Visit P4 site region

  • The street lamp foundation already start by today
  • The electric cables are completely installed

IMG20180807161220.jpg

2pm

  1. Visit P26 site region
  • Check the sewage pipe construction
  • For DN450 sewage pipe, only left about 20meter and expected to be completed by today
  • For DN600 sewage pipe, the materials will only reach by tomorrow
  • For DN900 sewage pipe (crossroad), the materials, labor and equipment are ready and will start tomorrow
  • Inform all the departments that going to do the crossroad sewage pipe tomorrow so will do the road closure

6pm

  • Off from work