Day 43 Internship at Forest City
by BOO WEN HAO
Day 43 Internship at Forest City
9am
- Visit P4 site region
- Check the progress for location amendment of power supply piping
- The front and middle part already finished and currently remove all the excess sands in order for constructing road foundation
- The rear part not yet finished as not clear with the boundary line of roundabout
- Inform the road contractor to ask road surveyor come and mark the boundary line
- Road surveyor will come during afternoon and then the rear part can be started
- Confirm tomorrow will connect all the electric cables
2. Help supervisor to do presentation slides
- Present all the informations about P4/P5/P26 site circumstances that going to be presented to the head director this afternoon
2pm
- Attend the weekly meeting
- Jot down the important notes about the next week plan
5pm
- Visit P4 site region
- Check the progress and the boundary line are already confirmed with road surveyor
- Confirm can completed by today and cables could be connected by tomorrow
2. Visit P26 site region
- Coordinate the contractor to put the marking for crossroad pipe and start to break the road structure (temporary)
- Check the progress for sewage pipe construction
- DN600mm sewage pipe will only come during next Monday
- Inform the contractor to dig the trenches and put the concrete foundation first
6pm
- Off from work