Day 55 Internship at Forest City
by BOO WEN HAO
Day 55 Internship at Forest City
9am
- At office
- Meet with the university supervisor - Prof Dr. Jamaliah
- Presentation session
- Allow supervisor to understand the task we've been doing, handling and also what we learnt
2pm
- Visit P26 site region
- All the crossroad pipes are completed during weekend
- On-site still left some concrete pieces and excessive pipe materials
- Coordinate the contractor in order to remove those materials so that do not block the path for road foundation construction
- Contact the consultant to ensure the application letter for water pressure test to SAJ have been submitted
- The water pressure test is estimated to be carried out by this week
6pm
- Off from work