Industrial training logbook

Day 28 Internship at Forest City

Day 27 Internship at Forest City

9am

  1. Visit P26 site region
  • At the rear end of P26, the drainage pipes location is wrong and already inform the related contractor to amend the location according to the latest design drawings
  • They make sure will complete in these two days hence the sewage piping can be started
  • At the middle part, some building materials like steel reinforcing bars are leftover and contact the project department to clear the site to ease the construction
  • Take some photos and send to the project department
  • At the front end of P26, the sewage piping construction holds as have to discuss with the related project department
  • Promise to fast dig trenches, put sewage pipe, construct layer of concrete on top and bottom of pipes then sand backfilling in order to create a space for vehicle to enter and leave
  • The sewage piping construction start as already seek permission from project department
  1. Visit P4 site region
  • The high-voltage power supply pipes recovery process start
  • Estimate to use 2-3 days to complete the process
  • The high-voltage power supply cables will be installed in this week
  • The low-voltage power supply (telekom) well undergoes backfilling and closing process

IMG20180718101341.jpg

  1. Visit International school region
  • Make sure the water meter had been installed completely and properly
  • Inform the contractor to settle the protruding well

2pm

  1. Visit International School region
  • Meet with the landscape department person to discuss the solutions about the protruding well
  • Decision: It is necessary to lower down the well
  • Inform the contractor to lower down the well height by breaking the upper structure

         2. Visit P26 region

  • At the front end of P26, the sewage pipe construction is ongoing
  • At the middle part, the water supply construction is ongoing
  • After discuss with the project department, The Giant Leap company confirm will clear the building materials by tomorrow hence the water supply construction can continue
  • At the rear end of P26, the sewage construction path is blocked by the China State Construction
  • Already meet and request the person in charge to move the building materials away from the path
  • They promise to clear the site and the sewage pipe construction can be start by tomorrow morning

6pm

  • Off from work