Day 28 Internship at Forest City
by BOO WEN HAO
Day 27 Internship at Forest City
9am
- Visit P26 site region
- At the rear end of P26, the drainage pipes location is wrong and already inform the related contractor to amend the location according to the latest design drawings
- They make sure will complete in these two days hence the sewage piping can be started
- At the middle part, some building materials like steel reinforcing bars are leftover and contact the project department to clear the site to ease the construction
- Take some photos and send to the project department
- At the front end of P26, the sewage piping construction holds as have to discuss with the related project department
- Promise to fast dig trenches, put sewage pipe, construct layer of concrete on top and bottom of pipes then sand backfilling in order to create a space for vehicle to enter and leave
- The sewage piping construction start as already seek permission from project department
- Visit P4 site region
- The high-voltage power supply pipes recovery process start
- Estimate to use 2-3 days to complete the process
- The high-voltage power supply cables will be installed in this week
- The low-voltage power supply (telekom) well undergoes backfilling and closing process
- Visit International school region
- Make sure the water meter had been installed completely and properly
- Inform the contractor to settle the protruding well
2pm
- Visit International School region
- Meet with the landscape department person to discuss the solutions about the protruding well
- Decision: It is necessary to lower down the well
- Inform the contractor to lower down the well height by breaking the upper structure
2. Visit P26 region
- At the front end of P26, the sewage pipe construction is ongoing
- At the middle part, the water supply construction is ongoing
- After discuss with the project department, The Giant Leap company confirm will clear the building materials by tomorrow hence the water supply construction can continue
- At the rear end of P26, the sewage construction path is blocked by the China State Construction
- Already meet and request the person in charge to move the building materials away from the path
- They promise to clear the site and the sewage pipe construction can be start by tomorrow morning
6pm
- Off from work