9am

  1. Visit International School region
  • Check the progress
  • Make sure the housekeeping is done completely

         2. Visit P4 site region

  • Check the progress of high voltage power supply well
  • Found out problem concerning the distance between the wells and inform the contractor come and fix it
  • Shift the well and connect the pipes
  • Urge the contractor to complete the construction latest by today as the cables will connected by tomorrow

         3. Visit P26 site region

  • At the front end, the sewage piping construction is ongoing and the materials for low voltage power supply construction is preparing
  • At the middle part, all materials had been removed and DN500 water supply pipe construction is ongoing
  • The water supply pipe along plot P26 is estimated complete by today
  • Tomorrow will have the air pressure test from SAJ Ranhill
  • At the rear end, already meet and urge the person in charge to clear the materials so that the sewage pipe construction could be initiated

2pm

  1. Attend the weekly presentation and jot down some important notes

5pm

  1. Visit various site region as supervisor will have leave on Friday, Saturday and Monday
  2. Supervisor hand over the task to me in order to check the site's progress and report to him

6pm

  • Off from work