Day 31 Internship at Forest CIty
by BOO WEN HAO
Day 31 Internship at Forest City
9am
- Visit International School region
- Check the progress
- Make sure the housekeeping is done completely
2. Visit P4 site region
- Check the progress of high voltage power supply well
- Found out problem concerning the distance between the wells and inform the contractor come and fix it
- Shift the well and connect the pipes
- Urge the contractor to complete the construction latest by today as the cables will connected by tomorrow
3. Visit P26 site region
- At the front end, the sewage piping construction is ongoing and the materials for low voltage power supply construction is preparing
- At the middle part, all materials had been removed and DN500 water supply pipe construction is ongoing
- The water supply pipe along plot P26 is estimated complete by today
- Tomorrow will have the air pressure test from SAJ Ranhill
- At the rear end, already meet and urge the person in charge to clear the materials so that the sewage pipe construction could be initiated
2pm
- Attend the weekly presentation and jot down some important notes
5pm
- Visit various site region as supervisor will have leave on Friday, Saturday and Monday
- Supervisor hand over the task to me in order to check the site's progress and report to him
6pm
- Off from work