Industrial training logbook

Day 62 Internship at Forest City

Day 62 Internship at Forest City

9am

  1. Visit P26 site region
  • Check the water pressure
  • The water pressure is currently 10bar and required to pump up to 12 bar then have a check on all valves along P26
  • After that, continue to pump the water pressure up to 15bar
  • SAJ requirements: 15bar water pressure have to maintain for 15minutes then decrease to 10bar and maintain for 24 hours

         2. Visit P4 site region

  • Check the landscape work progress as it is categorized as the inspection conditions

2pm

  1. Visit P26 site region
  • SAJ water pressure test is launched
  • The water pressure is pumped up to 15bar and maintain for 15minutes (PASS)
  • Decrease it to 10bar and required to maintain for 24 hours
  • Tomorrow 3pm SAJ will come again to check the water pressure
  • Tomorrow morning also will launch PDC7 inspection (CCTV test) on the sewerage pipe from IWK
  • Inform the contractor to check all the sewerage manholes are bricklayed properly

WeChat Image_20180829162701.jpg

 

6pm

  • Off from work