Day 62 Internship at Forest City
by BOO WEN HAO
Day 62 Internship at Forest City
9am
- Visit P26 site region
- Check the water pressure
- The water pressure is currently 10bar and required to pump up to 12 bar then have a check on all valves along P26
- After that, continue to pump the water pressure up to 15bar
- SAJ requirements: 15bar water pressure have to maintain for 15minutes then decrease to 10bar and maintain for 24 hours
2. Visit P4 site region
- Check the landscape work progress as it is categorized as the inspection conditions
2pm
- Visit P26 site region
- SAJ water pressure test is launched
- The water pressure is pumped up to 15bar and maintain for 15minutes (PASS)
- Decrease it to 10bar and required to maintain for 24 hours
- Tomorrow 3pm SAJ will come again to check the water pressure
- Tomorrow morning also will launch PDC7 inspection (CCTV test) on the sewerage pipe from IWK
- Inform the contractor to check all the sewerage manholes are bricklayed properly
6pm