Industrial training logbook

Day 34 Internship at Forest City

Day 34 Internship at Forest City

9am

  1. Supervisor is back and inform him about the current progress for P26
  2. Visit International School region
  • Take photo and inform the contractor come and fix it asap

         3. Visit P26 site region

  • The main reason for delay of sewage piping construction is due to the no coordination
  • Inform the contractor that they suppose to fence their site to prevent cars or anything from blocking their construction path
  • They also did not inform when there is blockage as we could help them to coordinate and remove the blockage
  • Urge the contractor to speed up the progress and OT everyday as the sewage piping construction should be completed before 10th August
  • As it will influence the CCC, the sewage piping construction have to be fast
  • The water supply piping still left 130m, but all the pressure gauge had been installed
  • The final inspection will be carried out by tomorrow and SAJ will come and do the pressure test by this week
  • Inform the person in charge to clear the drainage piping and building materials

         4. Visit P52 site region

  • Inform the contractor to complete the DN150 water supply piping as the road contractor shall start their construction

2pm

  1. Visit International School region
  • Inform the contractor that make sure complete the well and clean the surrounding by today as tomorrow gonna request the landscape department come and do turfing

         2. Visit P4 site region

  • Coordinate with the small municipal that gonna break part of the road structure in order to put the well

         3. Visit P26 site region

  • Take photos and send in the group
  • Help to coordinate with others to remove their materials hence the sewage piping construction can be started
  • The water supply piping process causing damage to temporary water supply pipe for small municipal
  • Fast fix the water supply pipe

         4. Visit temporary sewage treatment plant

  • There exist problem as the sewage not flowing
  • Found out problem as there is something wrong with the electrix box
  • Ask the responsible person come and fix this problem

 

6pm

  • Off from work