Day 41 Internship at Forest City
by BOO WEN HAO
Day 41 Internship at Forest City
9am
- Visit P4 site region
- Yesterday already inform the contractor not to put the sand on the road foundation
- Road contractor complain for putting the sand on the road foundation causing the gravel layer cannot be accomplished by today
- Quickly ask the contractor come and settle it now
- Contractor still facing short manpower
2. Visit P52 site region
- Inform the contractor to start the recycle water pipe by today
3. Visit P26 site region
- Check the sewage pipe construction progress
- The progress still too slow and perhaps might not be able to complete before 10th August for CCC
- Inform the contractor to OT everyday and try complete it on time
2pm
- Visit P4 site region
- Check the progress for installing the pipes 1m deeper
- Change the corrugated pipe into HDPE (uncorrugated) pipe
- Contractor move the machine for welding for connection to site
2. Visit P26 site region
- Check the progress for sewage pipe construction
6pm
- Volunteer to OT and continue supervise the P4 site region progress together with the supervisor as the cables are arranged to be connected tomorrow
11pm
- Off from work