9am

  1. Visit P4 site region
  • Yesterday already inform the contractor not to put the sand on the road foundation
  • Road contractor complain for putting the sand on the road foundation causing the gravel layer cannot be accomplished by today
  • Quickly ask the contractor come and settle it now
  • Contractor still facing short manpower

         2. Visit P52 site region

  • Inform the contractor to start the recycle water pipe by today

         3. Visit P26 site region

  • Check the sewage pipe construction progress
  • The progress still too slow and perhaps might not be able to complete before 10th August for CCC
  • Inform the contractor to OT everyday and try complete it on time

2pm

  1. Visit P4 site region
  • Check the progress for installing the pipes 1m deeper
  • Change the corrugated pipe into HDPE (uncorrugated) pipe
  • Contractor move the machine for welding for connection to site

 

         2. Visit P26 site region

  • Check the progress for sewage pipe construction

6pm

  1. Volunteer to OT and continue supervise the P4 site region progress together with the supervisor as the cables are arranged to be connected tomorrow

11pm

  • Off from work