9am

  1. Visit P26 site region
  • All sewage pipe had come and delivered on-site
  • Urge the contractor to make sure complete all the sewage pipe route along P26 by today
  • Check the crossover water and power supply pipe at front end of P26
  • Already send the pictures to SAJ and waiting further notice
  • Inform the contractor to check all the pressure gauge as SAJ might come for inspection by this week
  • Check the location of valve wall together with small municipal contractor (SMC)

IMG20180817090518.jpg

         2. Visit P52 site region

  • Meet with the small municipal to discuss about the crossroad power supply pipe which didn't appear on the large municipal design drawings
  • Decide to let our contractor to do the crossroad pipe
  • Write work memo to inform contractor to complete it by today as have to minimize the damage on the road foundation

2pm

  1. At office
  • Write work memo about penalty regarding to the work checklist signed by contractor

3pm

  1. Visit P26 site region
  • Check the sewage pipe construction progress

         2. Visit P52 site region

  • Check the crossroad power supply pipe construction progress

6pm

  • Off from work