Industrial training logbook

Day 48 Internship at Forest City

Day 48 Internship at Forest City

9am

  1. At office
  • Receive notice that Country Garden head company will send some crew for inspection on the safety and housekeeping issues of Forest City
  • Prepare materials and write work memo to notify the contractor to press on the issues and carry out relative preventive measures
  • Seek signature from head director of our department in order to proceed the work memo to contractor

         2. Visit P26 site region

  • Check sewage pipe construction progress
  • The connection of DN900 sewage pipe to STP is completed
  • The crossroad DN300 sewage pipe is completed as well
  • The slight tilt foundation for sewage pipe is in the fixing process, JCB is digging the trenches again
  • Meet some problems as building materials blocks the way for JCB moving
  • Coordinate and inform the related department to remove those building materials
  • DN600 sewage pipe materials still not delivered
  • The sewage pipe progress is about 70%

2pm

  1. Visit P26 site region
  • The sewage pipe construction progress is delayed due to the absence of pipe
  • Being informed that the pipe will only come tomorrow and 15th
  • Last time inspection from SAJ do not pass due to the distance between power supply manhole and water supply pipe do not meet the requirements
  • Contractor already do amendment
  • Check the pressure gauge along water pipe of P26 together with the contractor
  • The air pressure is satisfied and inform the contractor to fence the warning tape around the pressure gauge