Day 48 Internship at Forest City
by BOO WEN HAO
Day 48 Internship at Forest City
9am
- At office
- Receive notice that Country Garden head company will send some crew for inspection on the safety and housekeeping issues of Forest City
- Prepare materials and write work memo to notify the contractor to press on the issues and carry out relative preventive measures
- Seek signature from head director of our department in order to proceed the work memo to contractor
2. Visit P26 site region
- Check sewage pipe construction progress
- The connection of DN900 sewage pipe to STP is completed
- The crossroad DN300 sewage pipe is completed as well
- The slight tilt foundation for sewage pipe is in the fixing process, JCB is digging the trenches again
- Meet some problems as building materials blocks the way for JCB moving
- Coordinate and inform the related department to remove those building materials
- DN600 sewage pipe materials still not delivered
- The sewage pipe progress is about 70%
2pm
- Visit P26 site region
- The sewage pipe construction progress is delayed due to the absence of pipe
- Being informed that the pipe will only come tomorrow and 15th
- Last time inspection from SAJ do not pass due to the distance between power supply manhole and water supply pipe do not meet the requirements
- Contractor already do amendment
- Check the pressure gauge along water pipe of P26 together with the contractor
- The air pressure is satisfied and inform the contractor to fence the warning tape around the pressure gauge
6pm
- Off from work