Day 37 Internship at Forest City
by BOO WEN HAO
Day 37 Internship at Forest City
9am
- Meet with the contractor's consultant
- Discuss about the crossroad piping which haven't been constructed
- Discuss the coverage area should be handled by the contractor
- Discuss the invert level for manhole
2. Visit P26 site region
- Check the progress for sewage piping construction
- Sewage piping construction is blocked by the box culvert construction
- Coordinate with the road department and inform the contractor to skip that sensitive area and just move forward
- Concrete foundation is placed for sewage pipe
3. Visit P4 site region
- Still only left few persons doing high voltage power supply manhole
- Respond the circumstances to the contractor's boss and settle it asap
2pm
- Visit P4 site region
- Check the progress for high voltage power supply manhole
- Most of the manhole are completed with sand backfilling
- Urge the contractor must complete all the manhole by tonight
2. Meet with the Cost department to figure out the cost for the sand and concete pieces transportation
- Visit the P4/5/26 site region to calculate the areas required to transport sand and concrete pieces
6pm
- Off from work