Industrial training logbook

Day 37 Internship at Forest City

Day 37 Internship at Forest City

9am

  1. Meet with the contractor's consultant
  • Discuss about the crossroad piping which haven't been constructed
  • Discuss the coverage area should be handled by the contractor
  • Discuss the invert level for manhole      

         2. Visit P26 site region

  • Check the progress for sewage piping construction
  • Sewage piping construction is blocked by the box culvert construction
  • Coordinate with the road department and inform the contractor to skip that sensitive area and just move forward
  • Concrete foundation is placed for sewage pipe

         3. Visit P4 site region

  • Still only left few persons doing high voltage power supply manhole
  • Respond the circumstances to the contractor's boss and settle it asap

2pm

  1. Visit P4 site region
  • Check the progress for high voltage power supply manhole
  • Most of the manhole are completed with sand backfilling
  • Urge the contractor must complete all the manhole by tonight

         2. Meet with the Cost department to figure out the cost for the sand and concete pieces transportation

  • Visit the P4/5/26 site region to calculate the areas required to transport sand and concrete pieces

6pm

  • Off from work