Industrial training logbook

Day 47 Internship at Forest City

Day 47 Internship at Forest City

9am

  1. Visit P26 site region
  • Check the sewage pipe construction progress at the rear end
  • Instruct the sandbackfilling
  • DN600 pipe delivery process is delayed and cement mixture for foundation expected to do during afternoon
  • Supervise the progress
  • Verify another crossroad sewage pipe location DN300 according to the design drawing. This is for plot which not been developed yet

         2. Visit P52 site region

  • Check the sewage manhole closure
  • Inform the contractor to close the manhole and press on the safety and housekeeping issues

IMG20180809102046.jpg

2pm

  1. Visit P26 site region
  • Make sure all water meter are cared and fenced with the warning tape for SAJ inspection
  • Take photos and inform all related department to take care the meter
  • Check the sewage pipe construction progress at rear end
  • The pipe availables places are sand backfilling and already left a way that allow vehicles to travel
  • The cement foundation seems slight tilt and inform the contractor to fix it as it will affect the CCC inspection
  • The DN300 crossroad sewage pipe for future development plot start and estimated complete by today
  • The last sewage pipe that connects to STP3 will be completed by today

         2. Back to office

  • Write work memo: Inform contractor to remove all concrete pieces and the cost will be calculated by Cost Management Department
  • Write work meom: Inform contractor to press on the safety and housekeeping issues attached along with the photos as CGPV safety authority will come for inspection

6pm

  • Off from work