Day 47 Internship at Forest City
by BOO WEN HAO
Day 47 Internship at Forest City
9am
- Visit P26 site region
- Check the sewage pipe construction progress at the rear end
- Instruct the sandbackfilling
- DN600 pipe delivery process is delayed and cement mixture for foundation expected to do during afternoon
- Supervise the progress
- Verify another crossroad sewage pipe location DN300 according to the design drawing. This is for plot which not been developed yet
2. Visit P52 site region
- Check the sewage manhole closure
- Inform the contractor to close the manhole and press on the safety and housekeeping issues
2pm
- Visit P26 site region
- Make sure all water meter are cared and fenced with the warning tape for SAJ inspection
- Take photos and inform all related department to take care the meter
- Check the sewage pipe construction progress at rear end
- The pipe availables places are sand backfilling and already left a way that allow vehicles to travel
- The cement foundation seems slight tilt and inform the contractor to fix it as it will affect the CCC inspection
- The DN300 crossroad sewage pipe for future development plot start and estimated complete by today
- The last sewage pipe that connects to STP3 will be completed by today
2. Back to office
- Write work memo: Inform contractor to remove all concrete pieces and the cost will be calculated by Cost Management Department
- Write work meom: Inform contractor to press on the safety and housekeeping issues attached along with the photos as CGPV safety authority will come for inspection
6pm
- Off from work