Industrial training logbook

Day 51 Internship at Forest City

Day 51 Internship at Forest City

9am

  1. Visit P26 site region
  • Check the pipe amendment regarding the crossover of water and power supply pipe according to SAJ opinion
  • The distance between top of box culvert and bottom of water pipe must be greater than 700mm
  • But now distance only 400mm, inform contractor to remove the manhole first and increase the depth of power supply pipe
  • SAJ will come for inspection on Thursday morning
  • Tomorrow will check all the pressure gauge that must above 17bar
  • Elv pipe along P26 left 10meter

IMG20180814170736.jpg

2pm

  1. Visit P26 site region
  • Check the progress for pipe amendment
  • Inform contractor must complete by today and send pictures to SAJ
  • The Elv (Telekom) along P26 is completed
  • The DN600 sewage pipe will come tonight and tomorrow morning
  • The sewage pipe construction left 100meter and estimated completed by tomorrow
  • Coordinate with project department that will dig the trenches which will affect vehicle moving
  • Inform contractor start to do the crossover Elv pipe as the road foundation is ongoing

       2. Visit International School region

  • Inform contractor that there exist two parts happen water leakage
  • Observe contractor fix the problem
  • Inform landscape department to recover the surface of grass turfing

6pm

  • Off from work