Day 51 Internship at Forest City
by BOO WEN HAO
Day 51 Internship at Forest City
9am
- Visit P26 site region
- Check the pipe amendment regarding the crossover of water and power supply pipe according to SAJ opinion
- The distance between top of box culvert and bottom of water pipe must be greater than 700mm
- But now distance only 400mm, inform contractor to remove the manhole first and increase the depth of power supply pipe
- SAJ will come for inspection on Thursday morning
- Tomorrow will check all the pressure gauge that must above 17bar
- Elv pipe along P26 left 10meter
2pm
- Visit P26 site region
- Check the progress for pipe amendment
- Inform contractor must complete by today and send pictures to SAJ
- The Elv (Telekom) along P26 is completed
- The DN600 sewage pipe will come tonight and tomorrow morning
- The sewage pipe construction left 100meter and estimated completed by tomorrow
- Coordinate with project department that will dig the trenches which will affect vehicle moving
- Inform contractor start to do the crossover Elv pipe as the road foundation is ongoing
2. Visit International School region
- Inform contractor that there exist two parts happen water leakage
- Observe contractor fix the problem
- Inform landscape department to recover the surface of grass turfing
6pm
- Off from work