Day 57 Internship at Forest City
by BOO WEN HAO
Day 57 Internship at Forest City
9am
- Visit P26 site region
- The water pressure inspection test application letter already submitted to SAJ
- Due to Haji, it is estimated to launch the test during next Sunday
- Inform contractor to do the self testing for water pressure
- The machine is ready and inspect the water pressure
2. Visit P4 site region
- The street lamp foundation can be planted after confirming with road contractor
3. Visit International School region
- Leakage problem happens again
- Check the connection and found out the problem is due to the stone blocks the valve
- Take equipment and fix the leakage problem
2pm
- Visit P26 site region
- Meet with small municipal contractor to discuss the cross structure of pipes problems
- Discuss according to design drawings
- Come out with solutions that break the completed Elv pipe at first to allow the drainage box culvert pass through
- Small municipal contractor promise to recover the Elv pipe after the box culvert is completed
- At STP3, there happens small municipal contractor discharge the dosmetic sewage water into STP3 Inlet Chamber
- The excessive sewage water submerge the Inlet chamber and flow into Screen Chamber
- This incident cause the STP3 construction forced to postpone and require to clean the chamber
- Write work memo to project department to warn the above action and the charge for cleaning will be charged on project department
6pm
- Off from work