Day 2 Internship at Forest City
by BOO WEN HAO
Day 2 Internship at Forest City
9am
- Visit construction site
- Checking the progress of contractor on P-4 and P-5 regions
- Problem of water pipe keep cannot pumped to 15bar is identified, that means there must be certain reasons
- Identify the problem causing the delay of work (the underground pipe unable to pass the water pressure test)
- Analyse the possible reasons leading to problem
- poor connnection at interface,
- loose bolt and nut
- great vibration from heavy vehicles lead to crack in piping
2pm
- Checking the pipeline meetpoint whether exist leakage by digging out the valve
- Small accident happens as the mechanical digger machine cause damage on the TELEKOM piping
- Checking the pipeline is connected tightly
- Checking the progress at P-26 regions
- Check the well is installed and connected with the pipe then covered back with sand and clay
- The digging process is delayed as the digging machine in short
- Face-to-face communication with the contractor and discuss the solution to recover the delay progress
- Checking the location whereby construction work is carried out in order to make sure will not affect other company
6pm
- Off from work