Day 50 Internship at Forest City
by BOO WEN HAO
Day 50 Internship at Forest City
9am
- Visit P26 site region
- Check the progress of worklist
- Check all the pressure gauge along P26 and make sure above 15bar
- Some of the pressure gauge's pressure drop below 15bar and hence take photos and update to contractor come and fix it
- Today contractor's consultant go SAJ to discuss again the next inspection date after amendment
- Check the progress of sewage pipe construction
- DN600 sewage pipe keep getting delay and inform the contractor to coordinate and urge as supposed finished at 10th Aug
- Coordinate contractor to do the Elv Telekom pipe and last manhole as already left for one week
- Country Garden safety authorities come and check the site safety and found out the concrete foundation for sewage pipe not satisfied and meet requirements
- Inform contractor to redo the foundation and take photos hence send to authorities
2pm
- Visit P26 site region
- Opinion from SAJ regarding the crossover water and power supply pipe: using box culvert and make sure the distance between top of box culvert and bottom of water pipe must be greater than 700mm
- Coordinate the contractor come P4 and take the box culvert
- Check the progress for Elv (Telekom) pipe
6pm
- Off from work