9am

  1. Visit International School region
  • 2 manholes are completed and already inform the landscape department to do the final restoration work
  • Discuss with the landscape department to fix the protruding manhole about 10cm by using the soil to raise the surfaces of grass turfing

         2. Visit P4 site region

  • Still left 4 manhole not being chisel hole
  • Contractor still facing short manpower
  • Meet the contractor boss and bring him walk around P4 and see how bad the circumstances is
  • Urge the boss to come out with effective solutions as already affect others from doing work

2pm

  1. Meet with the contractor responsible for street lamp construction
  • Discuss according to the design drawing
  • Request the road contractor to mark the midpoint for roundabout
  • Estimate this weekend can start construct the foundation for street lamp

         2. Visit P4 site region

  • Check the progress

         3. Visit P26 site region

  • Check the progress for sewage pipe
  • Check the crossroad piping for water supply

IMG20180808091125.jpg

         4. Visit P52 site region

  • Check the progress for DN150 water supply pipe

6pm

  • Off from work