Day 54 Internship at Forest City
by BOO WEN HAO
Day 54 Internship at Forest City
9am
- Visit P26 site region
- The sewage pipe construction left 2 pieces of DN600 HDPE pipe
- Yesterday could not finish due to the unavailable transport for concrete
- Today morning could not do the concrete foundation due to heavy rain
- Estimated to finish all the sewage pipe construction by today
- Next week planning is finish all the crossroad pipe
2pm
- Attend the weekly meeting
4pm
- Visit P26 site region
- All sewage pipes construction are completed
- Discuss with road contractor and project department about road closure in order to do the crossroad pipe during this weekend
6pm
- Off from work