Day 40 Internship at Forest City
by BOO WEN HAO
Day 40 Internship at Forest City
9am
- Visit P52 site region
- Check the sewage snorkel construction progress and the Elv routing manhole
- The sewage snorkel is completed
- The manhole is incomplete and inform the contractor to complete it by today
2. Visit P26 site region
- Check the sewage pipe construction progress
- Check the Elv pipe construction progress
- Coordinate the road contractor to verify whether the sewage pipe is constructed at the right place
3. Visit P4 site region
- Check the progress for location amendment of Electrical manhole
- Inform the contractor to make the amendment fast in order not to affect road contractor to construct road foundation
2pm
- Visit P26 site region
- Check the sewage pipe construction progress
- Self inspection on the sewage pipe location using measuring tape according to design drawing
- Check the Elv pipe construction progress
- Elv routing complete but only left manhole haven't placed
- Inform the contractor to install the manhole
2. Visit P4 site region
- There is another manhole placed in the acceleration lane
- Need to fix the location of the manhole again
- Inform the contractor come and discuss the solutions
- Change the concrete manhole into cast iron manhole
- Inform the contractor try to fix these few days as don't want to affect road contractor doing road foundation
6pm
- Off from work