- Having short meeting with the head directior of Municipal Resources Department - Chen Ai Lu
- Self introduction about name, nationality, and educational background
- Having clearer understanding about the expectation from director
- Director request to write a short summary about what we did and learnt monthly in one page
- Giving comment about the working experience in forest city last week
- Giving opinions about supervisor
2pm
- Visit Forest City Golf Field working site
- Follow the supervisor and understand the design plan
- Having discussion with the contractor about the plan for installing underground power supply pipe
- Check the location for underground water supply pipe by referring the marking done by other contractor
- Uncertain location as the marking done is not clear
- The water supply pipe supposed to locate away about 1m above away from the power supply pipe
- It is better to install the water supply pipe before the power supply pipe
- Double check with the contractor responsible for installing water supply pipe
- Fully understand the design plan of water supply pipe
- Check the location of pipe along the roads
- The location of power supply pipe has to extend further away from the expected location
- Do marking for the power supply pipe
- Come out with agreement that the installation of power supply pipe should be done after the water supply pipe
6pm
- Off from work