Industrial training logbook

Day 6 Internship at Forest City

Day 6 Internship at Forest CIty

9am

  1. Having short meeting with the head directior of Municipal Resources Department - Chen Ai Lu
  • Self introduction about name, nationality, and educational background
  • Having clearer understanding about the expectation from director
  • Director request to write a short summary about what we did and learnt monthly in one page
  • Giving comment about the working experience in forest city last week
  • Giving opinions about supervisor

2pm

  1. Visit Forest City Golf Field working site
  • Follow the supervisor and understand the design plan
  • Having discussion with the contractor about the plan for installing underground power supply pipe
  • Check the location for underground water supply pipe by referring the marking done by other contractor
  • Uncertain location as the marking done is not clear
  • The water supply pipe supposed to locate away about 1m above away from the power supply pipe
  • It is better to install the water supply pipe before the power supply pipe
  1. Double check with the contractor responsible for installing water supply pipe
  • Fully understand the design plan of water supply pipe
  • Check the location of pipe along the roads
  • The location of power supply pipe has to extend further away from the expected location
  • Do marking for the power supply pipe
  • Come out with agreement that the installation of power supply pipe should be done after the water supply pipe

6pm

  • Off from work