Industrial training logbook

Day 30 Internship at Forest City

Day 30 Internship at Forest City

9am

  1. Visit International School region
  • Chisel the Elv (telekom) well till same level with the ground is ongoing
  • Take some photos that could added in the work memo
  • Inform the contractor to complete the process before 25th July as the school will open in August

IMG20180718093050.jpg

         2. Visit P26 site region

  • At the rear end of P26, the drainge pipe amendment is complete and the sewage piping can be started
  • Urge the related department to remove all the building materials asap
  • At the front end of P26, the sewage pipe construction is ongoing
  • At the middle part, all the building materials had been removed completely and now the DN500 water supply pipe can be started
  • Equipment is digging the trenches and estimated to complete the DN500 pipe today

         3. Visit P4 site region

  • Check the progress of high voltage power supply well construction
  • 12 wells should be constructed, now only 7 wells being placed but 3 of them haven't chisel the holes, there are 5 wells still not being transferred to site
  • Take some photos that could added in the work memo
  • Urge the contractor to complete the construction latest by tomorrow as the TNB will come and connect all the cables on Friday 20th July
  • Found out the main water supply well are not completed and workers idle on-site as there is no management person
  • Take some photos that could added in the work memo

2pm

  1. Help supervisor to write the work memo
  • International School low voltage power supply well chisel construction
  • Penalty for P4 site region: no management person, serious delay of construction and no sand backfilling after construction

         2. Visit International School region

  • Check the progress
  • Inform the contractor to clean the site after processing as the CEO will have a short visit around the Forest City by tomorrow

         3. Visit P4 site region

  • Check the progress of high voltage power supply well
  • Urge the contractor to make sure complete the construction by these two days
  • Check the progress of water valve completion
  • Take photos that could added in the work memo

6pm

  • Off from work