Day 30 Internship at Forest City
by BOO WEN HAO
Day 30 Internship at Forest City
9am
- Visit International School region
- Chisel the Elv (telekom) well till same level with the ground is ongoing
- Take some photos that could added in the work memo
- Inform the contractor to complete the process before 25th July as the school will open in August
2. Visit P26 site region
- At the rear end of P26, the drainge pipe amendment is complete and the sewage piping can be started
- Urge the related department to remove all the building materials asap
- At the front end of P26, the sewage pipe construction is ongoing
- At the middle part, all the building materials had been removed completely and now the DN500 water supply pipe can be started
- Equipment is digging the trenches and estimated to complete the DN500 pipe today
3. Visit P4 site region
- Check the progress of high voltage power supply well construction
- 12 wells should be constructed, now only 7 wells being placed but 3 of them haven't chisel the holes, there are 5 wells still not being transferred to site
- Take some photos that could added in the work memo
- Urge the contractor to complete the construction latest by tomorrow as the TNB will come and connect all the cables on Friday 20th July
- Found out the main water supply well are not completed and workers idle on-site as there is no management person
- Take some photos that could added in the work memo
2pm
- Help supervisor to write the work memo
- International School low voltage power supply well chisel construction
- Penalty for P4 site region: no management person, serious delay of construction and no sand backfilling after construction
2. Visit International School region
- Check the progress
- Inform the contractor to clean the site after processing as the CEO will have a short visit around the Forest City by tomorrow
3. Visit P4 site region
- Check the progress of high voltage power supply well
- Urge the contractor to make sure complete the construction by these two days
- Check the progress of water valve completion
- Take photos that could added in the work memo
6pm
- Off from work