Day 56 Internship at Forest City
by BOO WEN HAO
Day 56 Internship at Forest City
9am
- Visit P26 site region
- Check housekeeping issue as want to prevent from affecting the road foundation construction
- Coordinate the contractor to remove the concrete pieces
- Coordinate with the sewage treatment plant (STP) contractor to discuss the location of air ventilation pipe
- Come out with decision that will do the air ventilation pipe on Friday evening as minimize the burden of road closure
- Connect the last two pieces of DN900mm of sewage pipe (HDPE) into the STP
2pm
- Visit P26 site region
- Check all the sewage manhole is constructed completely with concrete
- At the front end of P26 left one crossroad power supply HDPE pipe and will be constructed after discussing with road and bridge contractor
- Inform contractor to complete all valve wall for DN700mm water supply MSCL pipe
- Urge the consultant to submit the application letter to SAJ for water pressure test
2. Visit International School
- Pipe leakage happens
- Inform contractor to come and fix this issue
- Observe the fixing process and make sure the leakage problem is solved
6pm
- Off from work