Industrial training logbook

Day 56 Internship at Forest City

Day 56 Internship at Forest City

9am

  1. Visit P26 site region
  • Check housekeeping issue as want to prevent from affecting the road foundation construction
  • Coordinate the contractor to remove the concrete pieces
  • Coordinate with the sewage treatment plant (STP) contractor to discuss the location of air ventilation pipe
  • Come out with decision that will do the air ventilation pipe on Friday evening as minimize the burden of road closure
  • Connect the last two pieces of DN900mm of sewage pipe (HDPE) into the STP

WeChat Image_20180821175738.jpg

2pm

  1. Visit P26 site region
  • Check all the sewage manhole is constructed completely with concrete
  • At the front end of P26 left one crossroad power supply HDPE pipe and will be constructed after discussing with road and bridge contractor
  • Inform contractor to complete all valve wall for DN700mm water supply MSCL pipe
  • Urge the consultant to submit the application letter to SAJ for water pressure test

         2. Visit International School

  • Pipe leakage happens
  • Inform contractor to come and fix this issue
  • Observe the fixing process and make sure the leakage problem is solved

WeChat Image_20180821175725.jpg

6pm

  • Off from work