9am

  1. Visit International School region
  • 3 manholes are completed and only left 2 manholes
  • Consider whether it is necessary to chisel the manhole
  • Will discuss with contractor and landscape department together and come out with possible solutions

         2. Visit P4 site region

  • Check the progress for high voltage power supply manholes
  • Inform the contractor to connect the small municipal cables into the manhole
  • Inform the contractor have to complete all the manholes followed by sand backfilling by today

IMG20180808110025.jpg

         3. Visit P26 site region

  • Check the progress for sewage piping construction
  • Check the progress for low voltage power supply piping construction
  • Urge the contractor to speed up the progress as the sewage pipe involve with CCC
  • Meet with the road contractor to check whether the location for the crossroad water supply pipe right or not

2pm

  1. Visit P26 site region
  • Urge the road contractor also speed up the progress for box culvert as it directly influence the progress for sewage piping
  • Check the progress for sewage piping construction
  • Inform the contractor transport the sand at the same time do sand backfilling for the pipe have been done
  • Confirm the foundation for sewage pipe will be done by today

         2. Visit P52 site region

  • Check the location for snorkel
  • The snorkel construction start today and have to be fast as it will influence the road construction

         3. Visit P4 site region

  • Check the progress for manholes

6pm

  • Off from work