Day 38 Internship at Forest City
by BOO WEN HAO
Day 38 Internship at Forest City
9am
- Visit International School region
- 3 manholes are completed and only left 2 manholes
- Consider whether it is necessary to chisel the manhole
- Will discuss with contractor and landscape department together and come out with possible solutions
2. Visit P4 site region
- Check the progress for high voltage power supply manholes
- Inform the contractor to connect the small municipal cables into the manhole
- Inform the contractor have to complete all the manholes followed by sand backfilling by today
3. Visit P26 site region
- Check the progress for sewage piping construction
- Check the progress for low voltage power supply piping construction
- Urge the contractor to speed up the progress as the sewage pipe involve with CCC
- Meet with the road contractor to check whether the location for the crossroad water supply pipe right or not
2pm
- Visit P26 site region
- Urge the road contractor also speed up the progress for box culvert as it directly influence the progress for sewage piping
- Check the progress for sewage piping construction
- Inform the contractor transport the sand at the same time do sand backfilling for the pipe have been done
- Confirm the foundation for sewage pipe will be done by today
2. Visit P52 site region
- Check the location for snorkel
- The snorkel construction start today and have to be fast as it will influence the road construction
3. Visit P4 site region
- Check the progress for manholes
6pm
- Off from work