Week 4 part 2

5/7/2018

Site visit at bridge 15 (Jalan kuari) with M&E engineer in preparation for next week's work. A sets of overhead TNB cable that cross along the interchange need to be layed underground. Also there are some utilities on the existing bridge that need to be relocated ( 2x 11kV TNB, 1x 415V TNB, and 2x water pipe).

Overhead crossing that needs to be relocated

Details

6/7/2018

Today we went for a site walk with sub contractor Niaga Bumidan for upcoming work at bridge 12 and villa sangkot. They did some measurement in preparation for the work. 

Then, Mr fahmi explained on RFWI inventory registry and tasked me and my fellow intern to update it.

In the afternoon, Me and my fellow intern went to B52 hulu langat interchange to snap pictures for inventory as requested by JKR. The purpose of the inventory report is to request work permit from JKR. In the process, we learn to read the construction drawing.

 

Water pipe on B52

Details