Week 2 part 2

21/6/2018

Assisted Site supervisor for on site duty. Task done on site are as follow:

- Finishing yesterday's survey on B52 and jalan bukit belacan (JKR poles number recording and identifying feeder pillar for the respective poles)

- Site walk wiith contractor (Bumidan Sdn Bhd) for upcoming duct space record (DSR) work at Jalan Bukit Belacan.

The purpose of DSR is to identify,verify and record the cabling system of the area; in this case telco cabling. DSR is done manually by opening cable manhole and competent worker record the cabling system in the manhole. Several manhole are usually opened during DSR session. Criteria recorded are as follow:

  • Type of cable
  • Cable size
  • Number of way (Ducting and subduct) 

JKR poles identification

Details

22/6/2018

Studied contracts between AZRB, consultants and subcontractors for M&E department job scope along the package 1 and 2 span. The contract describes in detail each party's responsibility and obligations. The project work for M&E  along package 1 & 2 includes Toll plaza and administration utilities, TNB and telco services relocation, water pipe relocation and etc. The department hires different subcontractors for each works. 

M&E Engineer (Mr Hazwan and Mr Fahmi) discussed and briefed on internships program plan.

 

23/6/2018

Filter inspection and service work for mini dam ampang intake with M&E team.

Mini dam 1

Details

Mini dam 2

Details