2/7/2018
Discussed on method for TNB relocation at B52 with M&E team. B52 relocation case are complicated and we need to liaise with TNB.
Prepared meeting summary for 28/6 subcontractor meeting (SEP).
3/7/2018
Learned some lettering format and some documentation function used in construction work. Infrastructural work involve lots of authority liaising which require official documentation.
4/7/2018
Learned about remove and replace (R&R) procedure and some of wall type used in highway construction. I went to meet resident engineer for RFWI approval. He advised us to liaise with C&S department for one of our relocation due to upcoming R&R procedure and wall placement may clash with our cable. I also learn about Request for information document (RFI).