27/8/2018
Went to B52 Jalan hulu langat to decide trial hole piloting location. Locations of trial holes need to be decided on site due to the fact of sites constantly changing and objects uncharted in the construction drawing.
28/8/2018
Went to bridge 15 Jalan kuari to measure end to end slope of the river crossing. The purpose of the measurement is to determine the suitability of poles placement for Telekom cables. The river crossing is determined to be 36 meters, the maximum pole to pole span for Telekom overhead cables is 35 meters. Me and Mr asri (M&E engineer) decided to hold a meeting to ask for Telekom's discretion on the crossing span length as the cables are for temporary use only.
29/6/2018
M&E team went for a site walk with consultant to oversee bridge 11 and Chainage 10,100 vehicular box culvert progress. For bridge 11, parapet wall frame are already installed and ready to be casted on site. we had a minor discussion on the conduit for street lighting on bridge, the issue are kept in view to be discussed with C&S department.