Week 2

18/6/2018

Public holiday

Image

Details

19/6/2018

Site surveying Jalan Hulu Langat B52, indentifying JKR feed pillar, measuring distance between each poles and determining their position at B52 road and Bukit belacan junction. At the site Mr Hazwan taught me about the basics of three phase overhead cabling and their applications. Today i am also introduced to a new intern Mohd Huzayev.

Studied Low Voltage ABC Manual and  Underground Cable System Design Manual given by Mr Hazwan. The manual explains about TNB standards on aerial bundled cable and underground cabling layout and applications. 

ABC cable manual (TNB)

Details

20/6/2018

Continued to study TNB standard underground cable design manual. Learned the basics cable theory, standard cable laying specification, accessories and procedures. Next, Mr Hazwan gives a detailed brief on the M&E department job scope for package 1&2.

Underground cable manual

Details