11/6/2018
Briefing by the HR executive Mr efaizil at AZRB HQ Kuala Lumpur. I was given the contact person for KLORR project that i need to report to.
Proceeded to report for duty at EKVE pakage 1&2 site office at jalan kuari sg Long, Hulu langat. There i was introduced to every staff at M&E department and briefed further on my specific task. Mr Hazwan briefed me on the current task of the M&E departmernt. I was given the main drawing of the EKVE project to be studied. At 3.00PM i was invited to observe a meeting between the AZRB KLORR M&E department and a project contractor (SEP engineering).
12/6/2018
Attended the weekly toolbox briefing. At the briefing I am asked to introduce myself to all package 1 & 2 staffs. Then, I went throught safety induction session with SHE and they gave me the appropriate personal safety equipment (PPE) (vest, safety boots and helmet).
At 10PM, I followed Mr Tajul (M&E package 2 site supervisor) for a site visit along a portion of package 1&2 project span. He taught me on how to interpret the construction drawing and identifying each object on site based on the drawing.Then, we visited AIR selangor to conduct volumetric flow rate measurement on the pipe sourced from mini dams constructed by AZRB for AIR selangor. In the evening, I did some calculation on the flow rate as requested by Mr Hazwan based on the data collected earlier in the morning.
13/6/2018
Tasked to revise memo and letter filing. Skim some of the memos and letter to keep up with the latest issue faced by the department. Briefed on function of each document i.e. memo is an internal document usually used to deliver information to other department
Mini dam pipe flowrate and NTU reading results tabulations for the reports requested by AIR Selangor.