Internship logbook in CGPV (Week 10)

Num.

Date

Day

Log/Activity

1

05-08-2018

Sunday

  • Company off day.

2

06-08-2018

Monday

  • After going to construction site at P4, P5 and P26, it is common for me to see reinforcement bar everywhere.
  • Therefore, I made some researches to understand better on its functions, material properties and mechanical properties.
  • Reinforcement bar which is also known as ‘rebar’ in its short form, is a steel bar or mesh of steel wires used as a tension device in reinforced concrete and reinforced masonry structures to strengthen and hold the concrete in compression.
  • Concrete is strong under compression but having weak tensile strength.
  • Rebar significantly increases the tensile strength of the structure. Rebar's surface is often patterned to form a better bond with the concrete.
  • Carbon steel is one of the most common type for rebar, which consisting of hot-rolled round bars with deformation patterns.
  • There are other popular types, for instance, stainless steel, and composite sections made of glass fiber, carbon fiber, or basalt fiber.
  • These alternate types tend to be more expensive or have lesser mechanical properties, which serve the purpose of fulfilling certain performance requirements.
  • 4.jpg.6
  • 5.jpg.3

3

07-08-2018

Tuesday

  • A rebar spacer is a device that secures the reinforcing steel or ‘rebar’ in reinforced concrete structures as the rebar is assembled in place prior to the final concrete pour.
  • The spacers are left in place for the pour to keep the reinforcing in place, and become a permanent part of the structure.
  • The main categories of rebar spacers are:
  1. Linear Spacers (Π-section profiles, H-section profiles, or other 3 dimensional shapes),
  2. Point Spacers (wheel spacers, various tower or chair-like shapes)
  • Rebar spacer can be divided in three main raw material categories, which are concrete spacers, plastic spacers and metal spacers.

4

08-08-2018

Wednesday

  • Since there is more free time in the afternoon, I made some researches on my future Final Year Project title.
  • Based on the conversation with the lecturer, I had decided to choose the research field of Stress Corrosion Cracking (SCC).
  • Stress corrosion cracking is the growth of crack formation in a corrosive environment, and SCC will lead to unexpected sudden failure of ductile metals subjected to tensile stress, especially at elevated temperature.
  • Special environment is critical for SCC to occur, as only low concentration of specific highly active chemicals is required for the material used (usually alloys are more commonly used).

5

09-08-2018

Thursday

  • Early in the morning, I followed Mr. Su to visit several places with purpose to check the water meter stand.
  • These places include Golf Hotel, P18 and nearby the Malay village.
  • We also went to check for the RMU installation in Nusajaya Tech Park, outside the Forest City.
  • Water pressure, water consumption, time were recorded under this inspection.
  • Abnormal pressure readings were noticed because of 2 reasons, which are low water pressure and SAJ shut down the water supply due to some misunderstanding.
  • If this problem is not solved, water meter stand has to be demolished and rebuild a new one to pump more water in order to fulfil the increasing daily water consumption.
  • 1.jpg.9
  • 2.jpg.12
  • 3.jpg.8

6

10-08-2018

Friday

 
  • In the morning, since there will be FKM supervisor, Prof Jamaliah’s visit to my company, I made some arrangements such as booking meeting room, lending projector as well as discussing with other interns on presentation sequence.
  • I spent some time to do the presentation slides which is going to be presented on next Monday (20 August 2018).
  • There was a weekly meeting after lunch break, from 2.30 pm to 4.30 pm in Design Studio meeting room.
  • The focus of the meeting was on PDC 7 of P26 and P23, water supply issue in Golf’s project and sewage system.
  • Chen Ai Lu also mentioned the importance of having time frame, maintenance and protection of water pipeline and electric cables.
  • He also emphasized on the feedback of problem occurred should be reported immediately to him, so that disturbance will not be done to other department or contractor. 

7

11-08-2018

Saturday

  • Company off day.