Week 9 (13/9/2020 - 19/9/2020)

14/9/2020 (Monday)

Working time: 8:30am – 6:00pm

  • I started my day by updating the daily yield as per request by Mr KL Tang before 9:00am.
  • Then, ST Chin came and requested some alterations on the BONAPARTE program.
    • I went to the OGP Machine and altered the previous program to fulfill the request from ST Chin.
  • After lunch break, Kak Ida and I went to SMT Department.
    • Today, a new machine arrived in P13. Kak Ida has to inspect the machine set up along with a vendor.
    • This newly arrived machine is a machine to determine the grouping of the PCB in a more advanced way.
    • After the setup is done, there will be training on how to handle the machine held by Mr Ong.
    • However, the set up and programming of the machine consumed more time than we expected.
    • Therefore, the training was postponed until tomorrow.

 

15/9/2020 (Tuesday)

Working time: 8:30am – 6:00pm

  • I started my day by updating the daily yield as per request by Mr KL Tang before 9:00am.
  • After that, Kak Ida and I went to inspect the machine.
    • The machine was fully setup with the programs.
    • Kak Ida and I searched out for some PCB to be tested on the machine.
    • The vendor stated that the machine utilisation was quite limited to certain product only due to the programming in the machine.
    • This means that if we wanted to use the machine on more product, we have to insert in new programs into the machine.
  • After lunch break, I helped Ibrahim on his task.
    • He was asked to inspect all machines that are available in MCOB and SMT Department.
    • We went through the process flow on each department and started the inspection from the very beginning of the product creation.
    • This task helped me understand each machine more in term of its utilisation and the process carried on in each machine.

 

16/9/2020 (Wednesday)

Hari Malaysia Holiday

 

17/9/2020 (Thursday)

Working time: 8:30am – 6:00pm

  • I started my day by updating the daily yield as per request by Mr KL Tang before 9:00am.
  • After that, I went to check on the tablet utilisation issue in MCOB A Department.
    • I asked around the operators on this issue and most of them already utilized the tablet fully.
  • After lunch break, I went to help Mr Shazni on some quick measurement he needed by today.
    • Mr Shazni asked me to write him the program and he will run it by himself.
    • Therefore, I spent some time figuring out the best program to measure the measurement needed and gave the program to Mr Shazni for further action.
  • Later, I went to SMT Department with Mr KL Tang.
    • We noticed that there was problem with one TV in SMT Department.
    • The TV was the one that uses the screen-mirroring technique to display the content from the PC nearby.
    • However, the PC nearby was fully occupied by the operators. Thus, screen-mirroring was disabled at that particular TV.
    • I asked Mr KL Tang to request for a new PC and a table to solve this problem.
    • Mr KL Tang contacted the technical team from P21 to ship out a PC and a table.

 

18/9/2020 (Friday)

Working time: 8:30am – 6:00pm

  • I started my day by updating the daily yield as per request by Mr KL Tang before 9:00am.
  • After that, I attended the online supervision held by UTM Supervisor, Dr Shaharil.
    • The supervision was attended by another trainee from UTM, Izzat along with my company supervisor, Mr KL Tang.
    • During the meeting, I presented the tasks I have done throughout my internship period.
    • There was a Q&A session between us. Dr Shaharil asked Mr KL Tang to give out some comments on my performance.
  • Later, I learnt how to evaluate data on cycle time from Kak Nurul.
    • Cycle time is the time to complete each process.
    • I extracted data from the ShopFloor and began evaluating and analyse the data according to requirement.
  • After lunch break, I went to MCOB A Department with Mr KL Tang.
    • There, we met with Ibrahim along with Mr Vincent, the Vice President of SMT Department.
    • Mr Vincent was settling an issue on the the separating machine.
    • Since I have no urgent matter to be done, I helped out Mr Vincent and Ibrahim to settle a few things regarding the separating machine issues.
  • For the TV issue, Mr KL Tang informed me that P21 technical team has approved on delivering a PC and a table as per requested.
  • The delivery will be done on the upcoming Monday.