Industrial Training Week 4
|
Day |
Date |
Description |
|
Monday |
2/7/18 |
- Visiting test cell. - To change the carbon seal on the front disc shaft at the front frame of the T58-GE100 engine. - Carbon seal needs to be changed because there is a leakage during testing. - If not critical, we can just do lapping.
|
|
Tuesday |
3/7/18 |
- Visit test cell. - The change of carbon seal still in progress. - Deliver T58-GE100 engine from engine shop to test cell so that the engine can be tested. - Doing final assembly on T58-GE100 engine that had been tested. - Doing finishing - Check the engine - Apply wire locking at nut and bolt for safety.
|
|
Wednesday |
4/7/18 |
- Deliver another T58-GE100 engine from engine shop to test cell so that the engine can be tested. - Watching engine test run at the test cell. - Greasing flexible drive shaft for T58-GE100 engine.
|
|
Thursday |
5/7/18 |
- Learn to do wire locking. - Wire locking is for safety. - Also to prevent nut and bolt from loose.
|
|
Friday |
6/7/18 |
- Converting T58-GE100 engine from No.1 to No. 2. - Only need to remove the power turbine section of the engine. - The parts on the side of the exhaust casing is switched 180 degree diagonally.
|