Industrial training-log book
Friday, 3rd August 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Engineering Central Store (ECS)/Ground service equipment building
0830: Arriving site office
1000: Replacing new pendaflour lamp, ballast and starter to replace with the old lamp at the office
1100: Drilling concrete floor at the vehicle maintenance workshop to provide yellow pole at workshop entrance proper base/footing.
1430: Installing bent steel reinforcement to hold the entrance pole
1600: Worked area housekeeping
1730: Going back home
- 06 August 2018, 10:33 AM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Thursday, 2nd August 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Ground service equipment building
0830: Arriving site office
1000: Servicing AHU at GSE building; Rinsing air-cond coil with water jet, and spraying chemical air-cond coil cleaner by pressure sprayer
1100: Waiting for the dirt inside the coil to coagulate/accumulate and rinse it with water
1200: Removing the AHU filters from inside AHU to remove the old filter cotton and replace it with a new one.
1430: Closing and securing AHU door
1500: AHU room housekeeping
1600: Installing new pipe at the sink
1700: Cutting excess bolt on the floor to avoid the worker from tripping
1730: Going back home
- 06 August 2018, 10:00 AM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Wednesday, 1st August 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Ground service equipment building
0830: Arriving site office
1000: Installing new pendaflour lamp to replace broke old pendaflour lamp at the turbine engine storage room
1100: Installing thin aluminium plate on the old door unit
1730: Going back
- 06 August 2018, 9:55 AM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Tuesday, 31st July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Hangar 06
0830: Arriving site office
1000: Installing new pendaflour lamp to replace broke old pendaflour lamp
1100: Troubleshooting the electrical control panel nearby
1430: Servicing air-conditioner split unit (ACSU) at the hangar 05 office
1730: Going back
- 06 August 2018, 9:51 AM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Monday, 30th July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Ground Service Equipment building
0830: Arriving site office
1000: Checking roller-shutter motor and power supply
1100: Installing new lamp to replace the broke pendaflour lamp.
1430: Checking/troubleshooting clogged drainage system at emergency eye-wash shower point.
1730: Going back
- 29 July 2018, 8:54 PM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Friday, 27th July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Engineering building
0830: Arriving site office
1000: Checking power supply for the drilling machine at the workshop.
1100: Installing warning sign at the temporary break-down machine.
1430: Inspecting riser and FM200 system.
1730: Going back
- 29 July 2018, 8:50 PM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Thursday, 26th July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, MAB Masjid.
0830: Arriving site office
1000:Mixing a concrete for laying process of the drilled wall.
1100: Laying a cement at the drilled wall.
1430: Open the water source to ensure there's no leaking and it is working in normal behavior.
1730: Going back
- 29 July 2018, 8:49 PM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Wednesday, 25th July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, MAB Masjid.
0830: Arriving site office
1000: Drill wall to replace embedded broke valve with a new valve
1100: Rubbing the PVC glue at the PVC pipe fittings
1430: Install new valve
1730: Going back
- 29 July 2018, 8:48 PM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Tuesday, 24th July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Engineering building.
0830: Arriving site office
1000: Disassembling the fittings of 100hp motor and removing the motor from track.
1430: Placing 100hp motor inside a truck for maintainance of the motor.
1730: Going back
- 29 July 2018, 8:48 PM MUHAMMAD ZAHIR BIN AHMAD
Industrial training-log book
Monday, 23rd July 2018, KFM solutions Sdn. Bhd.- Kompleks kejuruteraan MAB, Engineering building.
0830: Arriving site office
1000: Assisting MAB technician troubleshooting AHU control system.
1430: Found the 100hp motor are not operating
1730: Going back