Internship (WEEK 6)

30/7/2018 - 4/8/2018

  • Set up cabin before work started.
  • Attended safety induction (Petrofac) to gain access working at site and height.
  • 3 cabins consist of site office, QC office and store were located at site to ease work progress.
  • The management at site consists of:
    1. Project Manager
    2. Project Engineer
    3. Site Supervisors
    4. QC
  • The technical department consists of:
    1. Foreman
    2. Fitter
    3. Welder
    4. Electrician
    5. Semi-skill
    6. Helper
  • Each intern student was placed under different foreman.
  • My first task was to understand the drawing of the instruments layout and identify the location of each instrument from drawings given.
  • There are 2 types of system that need to be work on for our team which are Public Address and General Alarm (PAGA) system and underground TELEKOM system.