Day 40 Intern
Day40 (Week 8)
Date: 01.08.2018 (Wednesday)
|
Time |
Entry |
Remarks |
|
0740 |
Depart From Bukit Mentok |
|
|
0750 |
Arrive at Iman Offshore Punch card |
|
|
0800 - 0820 |
Kick start |
Review on daily work |
|
0830 – 1230 |
Issue Purchase order for LJ Inspection |
Purchase order for inspection on test piece in order to fulfill client requirement in order to ensure the product reliability. |
|
Issue Purchase requisition for Gelombang Timur Supply and Services |
Pn Na’iemah request for coverall complete with embroidery |
|
|
1300 - 1400 |
Lunch Break |
|
|
1400 - 1700 |
Go to LJ Inspection at Jaka |
Received the test piece report. |
|
Go to KSB to retrieved |
The report is verified by Mr. Afiq (MEMS) |
|
|
1700 |
Punch out and went home |
|
Image 1 : Test Piece that have been Weld by Tuan Syarizad. These test piece have completed the inspection and will be send t the Rapid Pengerang.